Anderson County Crews will be on FM 321 blading patches. Expect lane closures with flaggers and a pilot vehicle controlling traffic.
Anderson County construction projects updates:
The contractor is scheduled to continue work on roadway elements. The speed limit has been reduced to 60 mph throughout the project limits. Motorists should use caution when traveling through the project and expect lane closures and delays. Project consists of widening for a Super 2, including sub-grade work, surface treatment, base and surface hot mix asphalt, widening structures, bridge rail, MBGF, signage and permanent striping.
Cherokee County Rusk Maintenance will be performing base repair and edging on FM 1247. Expect daytime lane closures. Jacksonville Maintenance will be performing blade overlay on FM 851 between FM 343 and FM 241. Expect daytime lane closures with traffic controlled by flaggers.
Cherokee County construction projects updates:
FM 22 Safety Widening and Bridge Replacement Project
The contractor is scheduled to continue corrective work and construction on the bridge at Little Turnpike Creek. Flaggers will be present during construction hours. Expect daily lane closures when work is being done. The bridge will be closed during construction. The project will widen the existing roadway, replace three bridges and incorporate safety upgrades.
No work is scheduled this week. Expect delays on this corridor when construction is in progress. The project will widen and resurface the roadway, along with adding safety upgrades.
No work is scheduled this week. No lane closures will be in place. The project widens the existing roadway and incorporates safety upgrades.
No work is scheduled this week. Lane closures will be in place during construction. The project adds passing lanes and incorporates safety upgrades.
The contractor is scheduled to continue road work construction on driveway upgrades and structure extensions. Lane closures are anticipated during construction. The project will consist of pavement resurfacing.
The contractor will be working on sidewalks and signals on US 79 and US 69 between US 175 and Cherokee. Traffic control will consist of occasional lane closures and work outside of the roadway when the work is in progress (Monday-Thursdays, weather permitting). This is a safety project to update existing signals and add pedestrian signals, crosswalks, and curb ramps.
Gregg County construction projects updates:
Spur 63/McCann Road Bridge Project
This project is part of the City of Longview Guthrie Creek Trail project. It will consist of building a bridge over Guthrie Creek to allow bicyclist and pedestrians to travel under Spur 63. The traffic will be reduced to two lanes, one northbound lane and one south bound lane to allow the contractor to build half of the bridge. Traffic will be switched later to allow completion of the bridge construction. Expect delays.
This project consists of widening a two-lane road to four lanes with a center turn lane. This includes drainage structures, flexible base, curb and gutter, sidewalks, hot mix and pavement markings. Contractor will be extending culverts and constructing detours. There will be daytime lane closures. Expect delays.
This project consists of widening a two-lane road to four lanes with a center turn lane. This includes drainage structures, new bridge, flexible base, hot mix and pavement markings. Contractor will be extending culverts and constructing detours. There will be daytime lane closures. Expect delays.
Big Head Creek Bridge Replacement
This project consists of replacing the bridge structure on Big Head Creek. Construction duration is expected to last four months. Pentecost Rd. will be open to local traffic only. Alternate route will include taking Stone Rd. to US 259 BUS.
Henderson County Athens maintenance is scheduled to perform mill and inlay operations on SL 7 between US 175W overpass and SH 31E overpass on Monday and Tuesday. Expect lane closures. Crews are also scheduled to perform surface pavement repairs on FM 85 between SH 274 and FM 2613. Expect lane closures with flaggers controlling traffic.
Henderson County construction projects updates:
The contractor is scheduled to work on the new northbound bridge and roadway elements. Motorists should be prepared for lane closures and delays. The speed limit has been reduced to 50 mph throughout the project. The project consists of the construction of replacing bridges, approaches, grading, structures, asphalt concrete pavement (ACP) base, ACP surface, retaining walls, curb & gutter, MBGF, and pavement markings.
The contractor is scheduled to work on traffic signal supports on BUS 175. Motorists should be prepared for lane closures and delays. The project includes traffic signals, curb ramps and pavement markings.
Rusk County Rusk County crews will be performing mill and inlay on SH 135 in Overton on Monday. Expect lane closures with flaggers controlling traffic.
Rusk County construction projects updates:
This project consists of milling asphalt surface and replacing asphalt surface and new pavement markings. There will be daytime lane closures with two-way, one-lane traffic with a pilot car. Expect delays.
Smith County Tyler Maintenance will have a base crew on SH 135 in Arp at the four-way stop on Monday. Expect flaggers controlling traffic. Tuesday the crew will move to SH 64 east of Chapel Hill for base repair. Expect lane closures with flaggers controlling traffic. A second crew will be on US 271 near FM 2908 performing level-up operations. Expect lane closures with flaggers controlling traffic.
Smith County construction projects updates:
US 271 Rehab, Turn Lanes, and Pavement Overlay
Crews will be performing paving rehab operations on the NB side. The NB outside lane will be permanently closed with signs and channelizing devices for the affected section. Traffic control will be managed by flaggers as needed. The project consists of paving, structures, MBGF, and pavement markings from I-20 north to the Gregg County line. The portion from I-20 to FM 16 also includes turn lanes and pavement rehabilitation.
The contractor is scheduled for punch list items. Temporary lane closures are anticipated from 9 am to 4 pm. Drivers are encouraged to use caution as work continues on this corridor. The project will widen FM 2493 from two lanes to a four-lane divided roadway with a flush median.
No work is scheduled this week. Temporary lane closures will be in place. The work zone speed limit is 60 mph on US 69. The project consists of building a new US 69 bridge over FM 346.
The contractor is scheduled to continue placing mowstrip and metal beam guard fence and continue Anticipate lane closures while work is in progress. When in progress, hours will be from 8 p.m. to 5 a.m., Sunday through Thursday nights. Expect delays. The project will resurface the roadway, upgrade drainage structures, and repair bridge joints.
Sidewalks at various locations in Smith County
The contractor is scheduled to continue work on SH 110 in Troup. Daily lane closures are expected. The project is adding sidewalks along SH 64W in Tyler, SH 110W, and SH 135N in Troup.
The contractor is scheduled to place MBGF and mowstrip. Lane closures are possible during work. The project consists of improving drainage, culvert work, and guardrail upgrades.
The contractor is awaiting punch list. When work is in progress, hours will be 9 a.m. to 4 p.m. Lane closures will be in place when working on the metal beam guard fence and retrofit rail. The project consists of bridge maintenance and repair.
This project consists of widening on ramps and exit ramps, culverts, drainage upgrades, new metal beam guard fence and bridge rails on the Barber Road overpass, and asphalt overlay. No work this week on this project.
Tyler State Park Bridge and Resurfacing Project
No work is scheduled for this project. The project will consist of bridge and pavement resurfacing.
SH 110 & FM 346 Landscape Project
The contractor is scheduled to continue forming various landscape development. The project consists of landscape development.
Sign Replacement at Various Locations in Smith County
No work is scheduled this week. Lane closures are possible when work is in progress. The project will consist of replacing small roadside signs.
Whittle Street, CR 2110 and CR 289 Bridge Replacement Project
No work is scheduled on Whittle Street at West Mud Creek Tributary. The project replaces the existing bridge with a new structure.
No work is scheduled on CR 2110 at Kickapoo Creek. The project replaces the existing bridge with a new structure.
The contractor is scheduled to continue construction on the CR 289 bridge at Prairie Creek. The road is closed to through traffic. The project replaces the existing bridge with a new structure. The contractor will complete one bridge at a time. Weather permitting, the bridge is scheduled to be completed at the end of May.
Safety Improvement Project (Van Zandt, Anderson, Smith and Henderson County)
The contractor is scheduled to continue work on driveways and drainage structures on FM 850 in Smith County. Motorists should be prepared for lane closures and delays. The project includes grading, structure work, guard rail replacement and bridge rail upgrades.
The contractor is scheduled to begin shouldering up pavement edges. Nightly lane closures will be in place. Work will be done at night from 8 PM to 5 AM. Expect delays on this corridor when construction is in progress. Project consists of an overlay with TBPFC surface, ACP surface, planing, shoulder texturing and pavement markings.
No work is scheduled next week. Project will begin June 1st; bridges will be closed to through traffic during construction. Project consists of the replacement of the bridge at Mud Creek and Mud Creek Relief.
Van Zandt County Canton Maintenance will be overlaying isolated areas on FM 1861 between FM 316 and SH 19. Expect daytime lane closures with flaggers controlling traffic.
Van Zandt County construction projects updates:
I-20 MBGF Improvements (Van Zandt, Smith, and Gregg counties)
Crews will be addressing punch list items in Van Zandt County (eastbound and westbound). Lane closures will be in effect nightly and will be managed by message boards, channelizing devices and law enforcement officers. Seeding will be performed daily using a mobile operation managed by LEO’s and TMA’s. This project is to construct safety improvements consisting of upgrading metal beam guard fence and mow strip.
SH 19 Super Two Widening & Overlay
Crews will be laying hot mix on the southbound super-two section and extending drainage structures on the northbound side. Traffic control will consist of a southbound lane closure and will be managed by flaggers and a pilot car. The project consists of Super 2 work including grading, base repair, treated subgrade, flex base, OCST, PFC surface, structures, signs and pavement markings.
Crews will be grading and paving at CR 2708 and addressing punch list items on CR 2918. CR 2708 will be closed at the bridge for the remainder of construction. CR 2319 and CR 2918 are open to traffic and in the punch-list phase. Minimal impact to the traveling public is anticipated. The project consists of removing and replacing four bridges.
Wood County Maintenance crews are scheduled to blade overlay on FM 1799 between US 80 and FM 779. Expect one lane closure with flaggers and a pilot vehicle controlling traffic. Crews will also begin blade overlay on FM 2966 between FM 515 and SH 154. Expect one lane closure with flaggers and a pilot vehicle controlling traffic.
Wood County construction projects updates:
SH 37 Road Widening and PFC Overlay
Crews will be installing driveway culverts southbound. Traffic control will consist of daily shoulder closures managed with signs and truck-mounted attenuator. The project consists of base repair, level-up, spray paver, permeable friction course surface, structures, bridge rail, metal beam guard fence, and pavement markings.
The Texas Department of Transportation is responsible for maintaining 80,000 miles of road and for supporting aviation, maritime, rail, and public transportation across the state. Through collaboration and leadership, we deliver a safe, reliable, and integrated transportation system that enables the movement of people and goods. Find out more at TxDOT.gov. "Like" us on Facebook and follow us on Twitter.
Copyright 2022 • Texas Department of Transportation • All Rights Reserved • Disclaimer • Privacy & Security Policy • Accessibility 125 East 11th Street • Austin, Texas 78701